| 62 Avenue
Widening
52 Street to 62 Street, City of
Lloydminster
62 Avenue is a 4-lane divided truck route in
north west Lloydminster
that links access to the Hill Industrial subdivision. Work consisted
of new construction of the southbound lanes as well as coldmilling
and overlay of the northbound lanes.
Click to view project photos (images
open in a pop-up window)
_____
The scope of the work:
- Excavation - 30,000 m3
- Coldmilling - 24,000 m2
- Concrete curb & gutter - 3,400 l.m.
- Asphalt pathway - 1,400 l.m.
- Granular base - 23,000 tonnes
- Asphalt concrete pavement - 11,000 tonnes
|